Subcontractors Have Remedies Over A Site

26 June 2013 | Construction, Engineering and Infrastructure

What happens when a main contractor enters into business rescue proceedings or liquidation and a subcontractor finds itself not being paid despite having carried out work?

The Johannesburg Hight Court followed by the Supreme Court of Appeal had to deal with the issue a little while back.

Buzzard Electrical had carried out work for a main contractor, but was not paid because the main contractor went into liquidation. 

The subcontractor sued the owner for payment on the basis that the employer had benefited from his work, and had been unjustly enriched at his expense. The Supreme Court of Appeal ruled that in circumstances where contracts existed between the owner and the main contractor as well as the main contractor and the subcontractor respectively, then the subcontractor had to enforce his contractual rights against the main contractor. The court declined to order the employer to make payment.

Can a subcontractor maintain possession of the site until it receives payment?

The Johannesburg High Court had to deal with the issue in the Sandton Square Finance case. The judge held that where there was no valid claim for unjust enrichment, no right of retention of the site arose.

Despite the fact that our courts adopt the approach that a subcontractor generally does not have a claim against the owner or is able to exercise a lien against it, a subcontractor does have a remedy if an owner forces its way on to site and unlawfully dispossesses the subcontractor of its possession of the sire. Such a scenario occured in Port Elizabeth recently. The judge in that case ordered the employer to return possession of the site to the subcontractor, regardless of whether the subcontractor was entitled to exercise a lien or not.

It means that even if a subcontractor is not entitled to exercise a lien, there is still an obligation on the owner to go to courty and obtain an order confirming that it can retake possession of the site. The owner may not take the law into its own hands and forcibly remove a subcontractor from a site.

In summary, subcontractors may find themselves in a particularly vulnerable position when main contractors enter into business rescue proceedings or are liquidated, and may nor be successful when asking a court to force an employer to make payment. Steps should be taken by a subcontractor before starting work to ensure that their payment is secured.

ARTICLE BY

Partner
Tel: 031 536 8511

Download

CONTACT

DURBAN

Telephone: 031 536 8500

PHYSICAL ADDRESS
45 Vuna Close,
Umhlanga Ridge, 4319

POSTAL ADDRESS
PO Box 913, Umhlanga Rocks, 4320

GPS Co-ordinates: 29°43'45.9"S 31°04'19.3"E

JOHANNESBURG

Telephone: 010 015 5800

PHYSICAL ADDRESS
4 Sandown Valley Crescent, Sandton, Gauteng, 2196

GPS Co-ordinates: 26°06'09.0"S 28°03'02.7"E

CAPE TOWN

Telephone: 021 879 2516

PHYSICAL ADDRESS
801, 8th Floor, Touchstone House,
7 Bree Street, Cape Town, 8001 | Dx 74 Cape Town

GPS Co-ordinates: 33°55'3.644:"S 18°25'19.66"E

ENQUIRY

© Cox Yeats Attorneys 2024 | PAIA | Website by Loud Crowd Media