02 May 2005 | Construction, Engineering and Infrastructure Law
The High Court has, in a judgment recently handed down1 , clarified the scope of a builder’s lien and reiterated some of the relevant principles underpinning such a lien.
The facts were:
• that no work had been done;
• the only item of expenditure was R80 000,00 in respect of bricks;
• only some bricks had been delivered to site; and
• the expenditure was more than covered by the deposit paid, the court held that:
• a builder only has a lien over property where he has actually done work and he has no lien for work not yet done or expenses not yet incurred;2 and
• in order for a lien to arise, payment for the work or material concerned must be due and not merely owing or accrued.3
In the result, the court issued an order directing that Norvic vacate the property, restore possession of it to Ballinger and that it pay the legal costs.
It is worth considering the second finding of the court relating to a lien not being enforceable unless the debt relied on is due, owing and payable.
In most standard form contracts, there will be an obligation on the contractor to hand over the site at practical completion or first delivery stage at a time when inevitably the contractor has not been finally paid for all the work done. The contractor cannot at this stage refuse to give delivery on the grounds that he has a lien because he will be due money in the future.
It is a different matter however if at the time there is an amount due, owing and payable to the contractor, for example, in terms of a previous payment certificate which has been issued and which is due for payment but has not yet been paid. In such circumstances, the contractor can of course enforce his lien and refuse to give possession of the site despite practical completion having been achieved.
The principle was usefully summed up with reference to outstanding retention moneys in the Gallic Construction case as follows:
“The builder’s lien is a debtor and creditor lien, which is a right of retention for a debt ex contractu (cf Brooklyn House Furnishers (Pty) Ltd v Knoetze & Sons 1970(3) SA 264A at 270). By virtue of such a lien the creditor in possession of property can retain it against his debtor until he has been paid all that is due to him under his contract in respect of work done and expenses incurred upon the property (Land Bank v Mans 1933 CPD 16 at 24). But plainly the creditor can have no right, in disregard of a contractual provision regarding delivery, to retain the property, until he has been paid money which although owing is no yet due. Thus, under the standard form of building contract, retention moneys become payable only some months after the delivery of the contract work; plainly the builder cannot claim a jus retentionis in respect of retention moneys which are not yet due. In my view the general principle is accurately stated in Halsbury Laws of England 3rd ed vol 24 para 148 at 270:
‘The debt in respect of which a lien is claimed must be due not accruing. Therefore a contract for a particular mode of future payment which precludes any implied contract for immediate payment does not give rise to a lien even where labour has been expended on a chattel. It is immaterial whether the contract for future payment is an express contract or is implied from usage of trade.’
In the present case the completion date (and by implication the delivery date in terms of clause 18) was 29 February 1980. The payment applied for by the respondent on 25 February would not become due until several weeks thereafter. Thus no amount was due and payable as at the date the application was launched and hence the respondent was not entitled to rely upon a jus retentionis as a defence to that application.”
1R D Ballinger and Another v Norvic Diverse Systems CC and Another, High Court of South Africa (SECLD), Case No 461/05, date of judgment 24 February 2005
2United Building Society v Smookler’s Trustees and Galombick’s Trustee 1906 TS 623 at 631. 3Conreff (Pty) Ltd and Another v Gallic Construction (Pty) Ltd 1981(3) SA 73W, Nicholas J at 76G ff.