27 August 2012 | Construction, Engineering and Infrastructure Law
The Grahamstown High Court delivered a judgment on 17 May 2012 which serves as a reminder that our Courts are strict in requiring claims procedures set out in building contracts to be followed.
Radon Projects ("the contractor") was employed by N V Properties ("the employer") in terms of a JBCC Principal Building Agreement (May 1998 Edition).
Prior to practical completion being reached, the contractor submitted numerous extension of time claims in terms of clause 29.1.
In most instances the principal agent failed to adjudicate the claims, or otherwise rejected them.
Clause 40 of the 1998 edition of the JBCC Agreement provides that a disagreement between the employer and contractor must be determined by the principal agent within 10 working days of a request. Such decision is final and binding on the parties unless a further dispute notice is given within 20 working days. (This is similar to the provisions of clause 58 of the General Conditions of Contract for Construction Works issued by the South African Institution of Civil Engineering.)
The contractor failed to give the required notice to challenge the principal agent's decisions in terms of clause 40 in relation to the disputed claims which had been referred to him.
The employer argued that the principal agent's decisions were final and therefore there was no arbitral "dispute" between the parties.
This issue was referred to the Court for decision.
The Court recorded that:
The Court held:
Should you require further advice or assistance, please contact Alastair Hay - 031 536 8508 / ahay@coxyeats.co.za, Richard Hoal on 031 536 8511 / rhoal@coxyeats.co.za, Peter Barnard on 031 536 8514
/ pbarnard@coxyeats.co.za or Vuyo Mkwibiso on 031 536 8523 / vmkwibiso@coxyeats.co.za.